Kuiken Brothers Kitchen & Bath
Search Our Site
HomeKitchensBathsOther RoomsCountertopsPlanInstallationContact Us
Kitchens > Installation
Kitchens
Start Planning

Need Installation?

Contact Us




Cardella Project – Week One

Jessica & Chris Cardella came to Kuiken Brothers in Warwick for their new kitchen. They requested something where they could do informal entertaining, and that had some more old world charm than what they currently have. The challenge was to incorporate existing post and beam work within the kitchen and eating are into a functional and aesthetically pleasing place. They also wanted the bath right off of the kitchen to match.
What ensues is the diary of their project.


The existing kitchen has been cleaned of all its “goodies” and this the last time it will be seen like this. The existing cabinets are a medium raised panel oak, with a Corian countertop. Although it is still in decent condition, it is probably the original kitchen that was installed when the house was built in 1987.

eating area

Eating area view

dining room

View into dining room

shower

Existing shower

bath vanity

Existing bath vanity

Back to Top

Next step, demolition & rough construction…

bath vanity

Kitchen being protected with plastic.

bath vanity

Looking into the new bath.

bath vanity

The new shower area
with plumbing roughed in.

bath vanity

Shower elevation with new wonderboard.

bath vanity

Looking towards the sink area.

bath vanity

Old refrigerator elevation cleaned up.

bath vanity

Sink & range wall after drywall.

bath vanity

Sink and new refrigerator
elevation after drywall.

bath vanity

The existing beam detail
that we have to contend with.

bath vanity

The new vanity area

bath vanity

The new window & future sink elevation.

bath vanity

The shiny new dumpster gets broken in.

bath vanity

View towards the dining
room (left) & eating area (right).

bath vanity

View into what will be the
new corner for the kitchen layout.

bath vanity

View down the hallway & laundry

bath vanity

The new sub-floor is all installed.

Back to Top

Cardella Project – Week Three

After all of the demolition and rough-ins are completed, arrangements have been made for the cabinet delivery. This is when real progress is seen. The cabinets are unpacked and sorted out on the first day. The remainder of day one and all of day two are spent getting the cabinetry set and ready for the countertop template. The size of the project determines this actual schedule though. The appliances and sink(s) are delivered prior to the countertop template. Setting the appliances into their respective places ensures a proper fit of all critical items during the template. Although there is significant progress being made there is more work to be done.

Cabinets are being installed with rough openings

Cabinets are being installed
with rough openings for appliances.

Cabinets are being installed with rough openings

Cabinets are being installed.

Cabinets are being installed with rough openings

Day three and the cabinets are set
with trim. The blue tape is for laying
out decorative hardware.

crown trim

The crown and trim tie into the
existing post and beam work at the refrigerator.

Sub-Zero refrigerator

The built-in Sub-Zero refrigerator is almost complete.

furniture piece

The furniture piece is well under way - Cherry cabinetry, Beadboard splash, Black walnut top, and furniture feet all add to the detailing.

countertops templated

The countertops are being templated. Note the undercounter microwave is now installed.

island

The island is just about complete - the tape is for hardware layout and the opening is for an undercounter wine refrigerator.

pantry

The new pantry unit
where the refrigerator used to be.

sink and refrigerator elevation

The new sink and refrigerator elevation.
Note the undercounter opening for the
microwave in the island.

Back to Top

Cardella Project – Week Four

cabinetry

All of the tall cabinetry needed to be field fit and mitered around the existing post and beam work.

doors and trim

In addition to the new cabinetry & flooring, The existing doors and trim were replaced with paint grade items.

sink

The biscuit farm sink is a nice contrast to the cherry cabinetry.

cabinets and trim

The cabinets and trim are nearly complete just waitng on final electric, countertops and plumbing.

refrigerator

The nearly complete refrigerator elevation.

sink and window

The new farm sink and window

Sub-Zero

The new complete Sub-Zero refrigerator enclosure

new pantry unit

The new pantry unit where the refrigerator used to be.

view into the bath

View to the dining room- note the new doorway trim.

new vanity cabinet

The new vanity cabinet, awaiting a countertop and vessel sink.

furniture feet

The small details such as these furniture feet help to create the overall feel of the room and add a custom touch.

pantry notched for beam

The tall pantry cabinet needed to be notched for the beam, note the detailing within the cabinet to contend with existing beam work.

view into the bath

The view into the bath off the kitchen, almost complete with new window trim and a knee wall at the shower.

Back to Top

Cardella Project – Countertops are Installed!

The day has arrived for the countertop installation. The fabricator made a template approximately a week and a half ago. With the installation of the top the kitchen looks complete. The top material is Emprerador Light Marble in the kitchen and Emperador Dark Marble in the bathroom. The slabs for both rooms were selected at the stone supplier’s yard. This selection was done earlier in the project, and was a balance between the cabinet, plumbing and tile finishes to achieve the right look. While waiting for the tops, the walls have started to be painted, and the electrician has been in to finish up his end. Now with the countertops installed the plumber can finish up his end and get this kitchen and bath ready for use...

countertops installed with island

The new countertops are being installed note the island top has room for seating.

countertops installed and walls painted

The new marble countertops are being installed, note the walls are starting to be painted.

vanity layout with vessel sink

The new vanity layout with vessel sink, marble top and sconces to go left and right of the mirror.

shower with kneewall

The shower enclosure with the new marble kneewall cap.

vanity top with vessel sink

The new vanity top with the vessel sink.

view from dining area

View from the dining area into the kitchen after the countertops have been installed and walls painted.

view from dining area

View from the dining area towards the sink and range while the countertops are being installed.

Back to Top

Stay Tuned For More!

Home | Kitchens | Baths | Other Rooms | Countertops
Plan | Installation | Contact Us | Kuiken Brothers | Elmwood Supply

 

Site Design by Yellow House Graphic Design